One thing I had failed to fully consider was exactly how
much material goes into a SCIPS house.
EPS foam is wonderful insulation but when every panel has 9.5 inches of
foam it really adds up.
Background: the SCIPS
materials from GCT will add up to five tractor-trailer loads. This is broken down into two separate
orders: two loads to be followed by
three loads.
Challenge number
one was getting the material to the property.
The home-site is on a small private road. A very small private road. Deliveries from GCT were originally scheduled
to arrive on 52-foot flatbed trailers; however after the dispatcher visited the
property he and Larry worked with GCT to fit everything on 48-foot trailers
instead. I was worried that the drivers
would not be able to get the truck into the property so had made arrangements
to use the parking lot of the community center to unload if it became necessary. Luckily both truck drivers were skilled
enough to back from a narrow two-lane road onto a narrow one-lane road so we
didn’t have to go to the backup plan.
However it was quite a sight to see.
We had just enough room for one car to get by once the truck was positioned.
Challenge number two was getting the material off the truck
and stored on the property. There were
three types of materials:
- · the panels (bulky but light),
- · pallets of wire mesh (small and not too heavy) and
- pallets of mortar mix (small and very heavy).
The first big
limitation was that the forklift we had could only handle one ton loads and
there were two tons of mortar on each pallet.
This meant that half the bags on each pallet had to be manually
offloaded to a separate pallet before the remainder of the pallet could be
unloaded. It also doubled the amount of
space we needed for storing the material.
The next problem
was that the driveway was too narrow for the forklift to move the panels from
the unloading area to the storage area.
Most of the panels in the first shipment are 18’10” tall. This meant that the panels had to be taken
from the truck, unstrapped and moved, four at a time, to a lowboy trailer. Since I had decided to keep as many trees as
possible around the home site there was not enough room to turn the truck
around so the driver had to back all the way down the the 200 yard, winding
driveway with a full load, unload, and then drive back to the entrance to pick
up the next load. The only real hold-up
came when the driver of the lowboy trailer locked his keys in the truck, but
even so the freight company driver said we were quicker unloading than the
loading process at the factory.
After the success
of unloading the first load Larry scheduled the second load for the following
day and the unloading process went even quicker.
Storing the materials was simple: we had stocked up on pallets so the mortar
storage was simply a question of finding space near the home site and the
planned location for the mortar pump.
We
were able to store the panels off the ground on either dunnage from the truck
or 4-foot lengths of railroad tie. The
final step was to double-tarp the mortar and spread wood chips around the
panels which were not on pavement, to keep the rain from splashing the red
Georgia clay on them.
Now on to placing
the panels!
No comments:
Post a Comment